April 2005
|
Deck to be extended
|
The "before" images (contracted May 26)
|
To give the contractors the idea
|
This baby's gotta go
|
Yours truly took the railings off and dropped that rock wall in foreground |
Another shot of Gibraltar
|
Progress in September
|
The long range view
|
Cut-Rite drilled holes ...
|
... and Dexpan blew the rock apart
|
November Vic's crew dug 14 holes 48 inches deep by hand ...
|
... and filled them with concrete wheeled in from the road
|
Deck removed and concrete poured
|
Not seeing much progress
|
Rocks from the wall rolled down here
|
The framing rests on the concrete pilings
|
From the flagpole
|
Starting to see progress
|
Deck framing done by Greg's crew
|
From the old deck
|
November 11
|
Deck on temporary strut
|
Glass, finally on November 29
|
Staging all around
|
Eddie's crew took over for the glass
|
No roof yet
|
Floor and kneewal in, but no roof glass
|
So the tarp awaits the storm
|
Buttoned down for the night
|